08 / Getting it built
What has to happen first?
We have put the new homes on the map. Now imagine moving into one. You turn on the tap, flush the toilet and head out to work. The family needs those things to work on moving day. A plan for the neighbourhood twenty years from now will not get everyone through this morning.
An everyday illustration of service needs, not a guarantee that a particular project is funded or ready.
Bell McKinnon gives us somewhere to follow that thought. North Cowichan describes a walkable, mixed-use community whose infrastructure and amenities are expected to be paid for by development. Its local area plan was adopted in 2018, before the current OCP. There is already a history here, and an expectation about who will pay. [1] This history matters: the area’s planning did not begin with the 2022 OCP.
In October 2024, council approved a policy for phasing Bell McKinnon's development. It says something worth stopping over: once land has the zoning needed for the proposed development, the municipality generally cannot control when construction happens. Its phasing policy therefore deals with the order of rezoning. Council can guide which land comes forward first; the policy gives it no construction calendar it can simply enforce afterward. [2]
The policy tries to avoid scattered growth. It uses rezoning and building-permit thresholds to guide when later areas should come forward, with exceptions council can consider. A building permit still leaves another step: somebody has to build the homes. That difference matters when we picture the finished neighbourhood and start counting on everything around it. [2]
There is another problem hiding in the map. Property lines do not conveniently arrange themselves around the park or the land needed to manage rainwater. One owner may be asked to give up much more land than another. A second policy, approved the same day, sets out a way to spread that burden. Where a property supplies less than the policy's 21 per cent public-land benchmark, an applicant would be asked for a cash contribution. Where it supplies more, the municipality would try to buy the excess using the fund, if money is available. Roads sit outside that public-land benchmark. [3]
That last condition brings us back to the kitchen table. Agreeing that everyone will chip in is one conversation. Having enough money in the account when the bill arrives is another. The policy explains a way to collect and share costs. To find out whether it is doing the job, we need the account: what came in, what was committed and what was paid.
The plan was changing while this work continued. The municipality reports that council expanded the urban containment boundary north of Herd Road in November 2025 and restored the local area plan for that area. So we have to follow later decisions too. The OCP adopted in 2022 is the beginning of that record, and council keeps adding to it. [4]
By February 2026, North Cowichan was publicly describing a wider service problem. It reported about 10,500 proposed units in development applications, including 6,300 that could not be serviced without major water and sewer upgrades. It put shared treatment-plant upgrades close to $100 million and additional water and sewer upgrades at $150 million, and said substantial help from senior governments was needed. Those were municipality-wide estimates at that date. They were not Bell McKinnon's bill, money already spent, or a promise that every proposed home would be built. [5]
This gives our question about North Cowichan's size something firmer to stand on. We can follow a real limit: the capacity of the systems serving the homes, and the money needed to expand them. We can ask which work is funded and when it will be ready. We can compare that with the development being approved. That is how we begin to judge whether the future on the map can keep pace with the people being invited to live in it.
Sources, dates & what they establish
Source notes distinguish published records, attributed accounts and worked examples. A link to a live page may now show a later version.
Municipal Bell McKinnon overview: 2018 local-area plan and expectation that development pays for infrastructure/amenities. An expectation is not proof of receipts or full cost recovery.
Phasing policy approved October 16, 2024, pages 1–4: rezoning phases, permit thresholds and discretion. No guarantee of a construction calendar, current eligibility or completed housing.
Land-acquisition contribution policy, October 16, 2024, pages 1–3: 21% average public-land benchmark, valuation formula, exceptions and purchases conditional on funds. Not a flat 21% tax. Current fund balance/transactions not audited.
November 25, 2025 municipal update reports November 19 adoption of boundary/local-area amendments north of Herd Road. No blanket rezoning, funding or servicing approval inferred.
February 26, 2026 municipal release: roughly 10,500 proposed units, 6,300 without service capacity absent major upgrades; treatment upgrades near $100 million and additional water/sewer upgrades at $150 million. Dated municipality-wide estimates/advocacy, not a Bell McKinnon bill, secured funding or October 2026 capacity audit.